West Ashley City Office Building Expansion and GMP

Charleston

Summary

The city's new West Ashley office building project would grow by about $188,576 because the contractor wouldn't carry Builders Risk insurance as planned. The project is funded mostly by a future GO bond.

At a glance

Total mentions
2
Last 30 days
1

Last discussed Sep 8, 2026.

Impact analysis

💰Financial impact

Adds $188,576.04 to a $37.8 million construction contract backed by a future general obligation bond.

✅Who benefits

City employees and residents who will use the new West Ashley office building.

⚠️Who could be affected

Taxpayers indirectly bear the increased project cost through the future bond.

Mentions & discussions (2)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Charleston

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.